Close-up of the Hòa Bình wind power project worth VND 5,000 billion before operation

The Hòa Bình 1 wind power project is divided into two phases, with a total investment of over VND 5,000 billion. Phase 1 of the Hòa Bình 1 project, with a total capacity of 50 MW, has been connected to the national grid. Currently, investors are accelerating progress to complete Phase 2 of the project.

SNSong Ngọc

Close-up of the Hòa Bình wind power project worth VND 5,000 billion before operation

The Hòa Bình 1 wind power project is divided into two phases, with a total investment of over VND 5,000 billion. Phase 1 of the Hòa Bình 1 project, with a total capacity of 50 MW, has been connected to the national grid. Currently, investors are accelerating progress to complete Phase 2 of the project.

The Hòa Bình 1 wind power plant project is invested in by Phương Anh Investment Construction and Trading Company Limited.

The transformer station work package is ready for the energization of the VND 5,000 billion project.

The infrastructure of Phase 1 of the Hòa Bình 1 wind power plant project and Phase 3 of the Hòa Bình 1 wind power plant project share common infrastructure.

The project’s administration building is being rapidly completed.

Leaders of Bạc Liêu province and investors inspect the project’s progress.

The cable system leading from the wind turbine towers to the transformer station is ready.

The access bridge is decorated to be environmentally friendly for tourism. According to the investor: The entire bridge railing uses local, environmentally friendly wood. After completion of energization, the investor will put it into tourism operation.


Beautifully illuminated access bridge to the wind power plant before opening to tourism.


Phase 2 is being rapidly constructed.


Chicken farm preparing to serve tourists at the project.


Phase 1 of the project, constructed in Vinh Hau commune, Hoa Binh district, is currently in its final stages of construction, preparing to complete the final work packages and achieve power connection, with 13 electricity poles and a capacity of 50MW. For Phase 2 of the Hòa Bình 1 wind power plant project, construction is expected to commence in July 2020, featuring 13 wind turbine towers with a total capacity of 50MW, sharing infrastructure with Phase 1 of the Hòa Bình 1 wind power plant project.


The investor representative stated that the project is being implemented in two construction phases, with a total designed capacity of 100MW and a total investment of 5,223 billion VND. This is the project that achieved the earliest grid connection progress among the 21 wind power projects in Bac Lieu registered for the first phase of operation (following the Bac Lieu wind farm which has been operating since 2017).

On July 5th, the Bac Lieu Provincial People's Committee announced that Phase 1 of the Hòa Bình project successfully connected to the national grid on July 3rd.


Phase 2 of the project is underway and will commence in July 2020, with early completion expected before October 30th due to shared infrastructure. All system access roads, cables, and turbine towers have been assembled and stockpiled at the project site.

The project’s guesthouse, designed with environmental friendliness, is preparing for tourism operation.

According to: NHẬT HỒ/laodong.vn

  • #song ngọc
  • #tin tức
ShareFacebookZalo

Related Articles

All Articles
Long Son Petrochemical Project UpdateNews

Long Son Petrochemical Project Update

On February 24th, the Southern Petrochemical Complex (Long Son Petrochemicals - LSP) with a total investment of $5.4 billion USD held a gro…